Irrigation Upgrade Works for Genders Park are set to commence late January 2025.
It is anticipated that works will take approximately 4 weeks to complete. The works will be undertaken in stages over the 4 week period from 7am to 4pm Monday to Friday.
What to expect
Open trenching by mechanical digging will be undertaken with all trenches being backfilled and compacted at the completion of each days work.
Please note, there will be staff, vehicles and machinery working in the park for the duration of works. It is requested that residents please be aware of any signage/safety barriers in place and adhere to safety requirements.
Why is the irrigation being upgraded?
The new irrigation system will provide an improved system for irrigating the park, providing water where it is required and reducing/removing water application where less water is required (Eco Zoning).
You can read more about this project on the Genders Park Project page on the Town's YourSay community engagement platform.
The Town apologises for any inconvenience caused during this period.
For further information, please contact The Town.
Share Genders Park update April 2024 on Facebook
Share Genders Park update April 2024 on Linkedin
Email Genders Park update April 2024 link
All submissions have been compiled and reviewed following conclusion of the consultation period for the draft Genders Park SOS Masterplan concept. As part of the review process, further work was undertaken to develop a Town wide approach to groundwater management and rationalisation in response to future reductions in groundwater use to be imposed by the regulator in 2028. This is an ongoing body of work which is required to guide future management of this resource to align with the community’s expectations for open space provision and presentation. As a result of the review process, some minor changes have been made to the concept plan. An overview of the changes is provided below:
A reduction in the overall size/area of proposed ‘Eco zone’ will provide a more balanced approach to the competing needs of the community, whilst still meeting the overall objective of reducing groundwater use. Transformation of the grassed verge area between the footpath and roadway along McCabe Street to Eco zone planting will remain. The existing established Eco zone adjacent to the eastern boundary of the park will remain ‘as is’ and the proposed Eco zone to the south has been reduced.
- Relocation of the BBQ, picnic table and shelter from the current location as indicated to take advantage of improved vistas and improved passive surveillance for park users. The location on the drawing is indicative and will be determined more accurately when replacement is required in future years.
Replacement and relocation of several bench seats, in accordance with disability access standards, to place these on concrete pads connected to the path and with arm rests. The bench seat in the central grass area will be relocated to take advantage of afternoon shade provided by adjacent trees and to open up the area allowing better access for informal kicking, hitting and throwing games.
- The Town is planning to undertake procurement during May 2024 to appoint a contractor to install a new reticulation system based on the SOS Master Plan. Once a contractor has been appointed, the reticulation installation project is expected to commence over the winter months and be completed before the next summer watering season.