10 December 2022

Consultation Commences

04 February 2023

Consultation Concludes

27 June 2023

Revised Draft LPP32 seeks approval to re-advertise for further Community Consultation

Following initial engagement with community and changes made to LPP32 based on input and feedback, the revised draft LPP32 will go back to Council to seek approval to readvertise for further engagement.

12 July 2023

Community Consultation and Engagement on Revised Draft LPP32 Commences

Following Council approval for further community consultation engagement, community will be able to contribute feedback and input into the revised draft LPP32 for a period of 42 days.

24 August 2023

Community Consultation and Engagement on Revised Draft LPP32 Closes

September 2023

Submissions under Review

Following an engagement period of 42 days, Town staff will review and assess submissions. Any revisions or further work to revised draft LPP32 will occur during this time.

28 November 2023

Council adopted LPP32

Final approval was sought, and Council subsequently adopted LPP32 at its Ordinary Council Meeting of 28 November 2023.