Glyde Street - Streetscape Master Plan
Delivering the vision for Glyde Street
The Glyde Street Streetscape Masterplan sets out a long-term vision to transform Glyde Street into a greener, more welcoming, and accessible town centre that supports local businesses and creates a vibrant place for the community to enjoy.
Following extensive community engagement, Council endorsed the Masterplan in 2025. The project has now moved into the delivery phase, with improvements to be implemented in stages.
View the endorsed Masterplan here.

Stage 1 construction 2026
Stage 1 construction is scheduled to commence mid-September 2026 (subject to materials delivery) and will focus on improvements along the northern side of Glyde Street.
Works include:
- New paving and widening of the northern footpath.
- Installation of new bicycle racks outside Samsons Paddock.
- Permeable paving, tree pits and new trees in front of 1 Glyde Street.
- Additional street tree planting and verge improvements.
These works represent the first stage of delivering the endorsed Masterplan and are designed to improve pedestrian comfort, increase greenery and enhance the overall streetscape.
A staged approach
The Glyde Street Revitalisation will be delivered progressively over time. While Stage 1 focuses on improvements that can be delivered now, detailed design for future stages is continuing to support the implementation of the remaining elements of the endorsed Masterplan.
We'll continue to provide updates as key project milestones are reached, including future design progress, construction planning and upcoming works.
Delivering the vision for Glyde Street
The Glyde Street Streetscape Masterplan sets out a long-term vision to transform Glyde Street into a greener, more welcoming, and accessible town centre that supports local businesses and creates a vibrant place for the community to enjoy.
Following extensive community engagement, Council endorsed the Masterplan in 2025. The project has now moved into the delivery phase, with improvements to be implemented in stages.
View the endorsed Masterplan here.

Stage 1 construction 2026
Stage 1 construction is scheduled to commence mid-September 2026 (subject to materials delivery) and will focus on improvements along the northern side of Glyde Street.
Works include:
- New paving and widening of the northern footpath.
- Installation of new bicycle racks outside Samsons Paddock.
- Permeable paving, tree pits and new trees in front of 1 Glyde Street.
- Additional street tree planting and verge improvements.
These works represent the first stage of delivering the endorsed Masterplan and are designed to improve pedestrian comfort, increase greenery and enhance the overall streetscape.
A staged approach
The Glyde Street Revitalisation will be delivered progressively over time. While Stage 1 focuses on improvements that can be delivered now, detailed design for future stages is continuing to support the implementation of the remaining elements of the endorsed Masterplan.
We'll continue to provide updates as key project milestones are reached, including future design progress, construction planning and upcoming works.
-
Stage 1 Landscape Works — Parking & Access Changes
Share Stage 1 Landscape Works — Parking & Access Changes on Facebook Share Stage 1 Landscape Works — Parking & Access Changes on X (formerly Twitter) Share Stage 1 Landscape Works — Parking & Access Changes on Linkedin Email Stage 1 Landscape Works — Parking & Access Changes linkThe Town of Mosman Park and its contractor, UGC Group, will carry out landscape construction works on Glyde Street, Mosman Park - including new paving, garden beds and landscape upgrades - from Tuesday 29 September to Friday 16 October 2026, under an approved Traffic Management Plan (TMP LGCPL-11796).
Works are confined to the northern (eastbound) side of Glyde Street only, from Stirling Highway to Monument Street. This notice covers the resulting parking changes, and how we're minimising impact on local businesses.
Project
Glyde Street Stage 1 Landscape Works
Works include
New paving, garden beds and landscape planting
Affected side
Northern (eastbound) side of Glyde Street only - Stirling Highway to Monument Street
Works period
Tuesday 29 September 2026 to Friday 16 October 2026
Working hours
7:00am - 5:00pm (In accordance with TMP LGCPL-11796)
Principal
Town of Mosman Park
Contractor
UGC Group
Parking arrangements
Approximately 3-4 bays directly in front of the active work area will be coned off at a time. This is a rolling closure that moves with the works - bays are reopened as soon as they're no longer needed.
- Only bays on the northern side, next to the work zone, are affected - all other parking on Glyde Street stays open.
- Cones and flagging will clearly mark affected bays, per the approved Traffic Management Plan.
- Usage of Parking Bays for works will be kept to a minimum, where practicable.
Minimising disruption to businesses
We're committed to keeping impact on local businesses to a minimum, with works sequenced so no property is disrupted longer than necessary.
- UGC Group will contact each affected business directly before works reach their frontage, to discuss access and needs.
- We’ll tailor bay timing, delivery windows and detours around your business needs wherever possible.
- Driveway access will be kept clear as far as practicable, with traffic staff on hand to assist vehicles in and out.
- Let us know early about events or peak trading periods so we can plan around them.
What to expect on site
- Traffic cones, flagging and high-visibility site staff around the work zone.
- Occasional noise and dust from demolition, earthworks and paving.
Contact us
Questions, or need specific arrangements for your business? Get in touch:
- UGC Group - Rish Pasha (Project Manager) - 0481 955 118 / rishaan.pasha@ugcgroup.com.au
- UGC Group - General Enquiries - info@ugcgroup.com.au
- Town of Mosman Park - (08) 9383 6600 / admin@mosmanpark.wa.gov.au
Thank you for your patience while we deliver these streetscape improvements.
The Town of Mosman Park and its contractor, UGC Group, will carry out landscape construction works on Glyde Street, Mosman Park - including new paving, garden beds and landscape upgrades - from Tuesday 29 September to Friday 16 October 2026, under an approved Traffic Management Plan (TMP LGCPL-11796).
Works are confined to the northern (eastbound) side of Glyde Street only, from Stirling Highway to Monument Street. This notice covers the resulting parking changes, and how we're minimising impact on local businesses.
Project
Glyde Street Stage 1 Landscape Works
Works include
New paving, garden beds and landscape planting
Affected side
Northern (eastbound) side of Glyde Street only - Stirling Highway to Monument Street
Works period
Tuesday 29 September 2026 to Friday 16 October 2026
Working hours
7:00am - 5:00pm (In accordance with TMP LGCPL-11796)
Principal
Town of Mosman Park
Contractor
UGC Group
Parking arrangements
Approximately 3-4 bays directly in front of the active work area will be coned off at a time. This is a rolling closure that moves with the works - bays are reopened as soon as they're no longer needed.
- Only bays on the northern side, next to the work zone, are affected - all other parking on Glyde Street stays open.
- Cones and flagging will clearly mark affected bays, per the approved Traffic Management Plan.
- Usage of Parking Bays for works will be kept to a minimum, where practicable.
Minimising disruption to businesses
We're committed to keeping impact on local businesses to a minimum, with works sequenced so no property is disrupted longer than necessary.
- UGC Group will contact each affected business directly before works reach their frontage, to discuss access and needs.
- We’ll tailor bay timing, delivery windows and detours around your business needs wherever possible.
- Driveway access will be kept clear as far as practicable, with traffic staff on hand to assist vehicles in and out.
- Let us know early about events or peak trading periods so we can plan around them.
What to expect on site
- Traffic cones, flagging and high-visibility site staff around the work zone.
- Occasional noise and dust from demolition, earthworks and paving.
Contact us
Questions, or need specific arrangements for your business? Get in touch:
- UGC Group - Rish Pasha (Project Manager) - 0481 955 118 / rishaan.pasha@ugcgroup.com.au
- UGC Group - General Enquiries - info@ugcgroup.com.au
- Town of Mosman Park - (08) 9383 6600 / admin@mosmanpark.wa.gov.au
Thank you for your patience while we deliver these streetscape improvements.
-
Stage 1 Construction Update August 2026
Share Stage 1 Construction Update August 2026 on Facebook Share Stage 1 Construction Update August 2026 on X (formerly Twitter) Share Stage 1 Construction Update August 2026 on Linkedin Email Stage 1 Construction Update August 2026 linkStage 1 construction update – August 2026
We know the community has been looking forward to seeing the Glyde Street works get underway.
Due to delays with material lead times, Stage 1 construction is now expected to commence in early to mid-September 2026.
Stage 1 construction update – August 2026
We know the community has been looking forward to seeing the Glyde Street works get underway.
Due to delays with material lead times, Stage 1 construction is now expected to commence in early to mid-September 2026.
-
Stage 1 Construction Update
Share Stage 1 Construction Update on Facebook Share Stage 1 Construction Update on X (formerly Twitter) Share Stage 1 Construction Update on Linkedin Email Stage 1 Construction Update linkStage 1 construction 2026
Stage 1 construction is scheduled to commence on 17 August 2026 (subject to materials delivery) and will focus on improvements along the northern side of Glyde Street.
Works include:
- New paving and widening of the northern footpath.
- Installation of new bicycle racks outside Samsons Paddock.
- Permeable paving, tree pits and new trees in front of 1 Glyde Street.
- Additional street tree planting and verge improvements.
These works represent the first stage of delivering the endorsed Masterplan and are designed to improve pedestrian comfort, increase greenery and enhance the overall streetscape.
To view the detailed plans please refer to the Documents tab on the right.Stage 1 construction 2026
Stage 1 construction is scheduled to commence on 17 August 2026 (subject to materials delivery) and will focus on improvements along the northern side of Glyde Street.
Works include:
- New paving and widening of the northern footpath.
- Installation of new bicycle racks outside Samsons Paddock.
- Permeable paving, tree pits and new trees in front of 1 Glyde Street.
- Additional street tree planting and verge improvements.
These works represent the first stage of delivering the endorsed Masterplan and are designed to improve pedestrian comfort, increase greenery and enhance the overall streetscape.
To view the detailed plans please refer to the Documents tab on the right. -
Masterplan adopted by Council
Share Masterplan adopted by Council on Facebook Share Masterplan adopted by Council on X (formerly Twitter) Share Masterplan adopted by Council on Linkedin Email Masterplan adopted by Council link
Council adopted the Glyde Street Streetscape Masterplan at Ordinary Council Meeting 29 July 2025, along with a series of resolutions for the Town to action alongside detailed designs and priority upgrades.
The priority upgrades will be progressed in consultation with our community to bring the shared vision for Glyde Street to life. For more detail on the Council resolutions, please see link above.
Thank you to everyone who shared their ideas and feedback, your input has helped guide the direction of our future planning.
Council adopted the Glyde Street Streetscape Masterplan at Ordinary Council Meeting 29 July 2025, along with a series of resolutions for the Town to action alongside detailed designs and priority upgrades.
The priority upgrades will be progressed in consultation with our community to bring the shared vision for Glyde Street to life. For more detail on the Council resolutions, please see link above.
Thank you to everyone who shared their ideas and feedback, your input has helped guide the direction of our future planning.
-
Notification of Ordinary Council Meeting – Glyde Street Streetscape Masterplan Final Adoption
Share Notification of Ordinary Council Meeting – Glyde Street Streetscape Masterplan Final Adoption on Facebook Share Notification of Ordinary Council Meeting – Glyde Street Streetscape Masterplan Final Adoption on X (formerly Twitter) Share Notification of Ordinary Council Meeting – Glyde Street Streetscape Masterplan Final Adoption on Linkedin Email Notification of Ordinary Council Meeting – Glyde Street Streetscape Masterplan Final Adoption linkThe final masterplan is being considered by Council for adoption at the July Council Meetings 2025 as follows:
- Agenda Forum – Tuesday 22 July 2025
(Discuss and seek points of clarification)
- Ordinary Council meeting - Tuesday 29 July 2025
(Decision making meeting)
Both meetings are open to the public to attend which are held at the Town’s Administration Centre, 1 Memorial Drive, Mosman Park at 6pm.
Presenting to Council
If you would like to present to Councillors at either meeting, or both, please complete a Deputation form and send it directly to: eo-ceo@mosmanpark.wa.gov.au and admin@mosmanpark.wa.gov.au before the meeting. Deputation forms can be found here: https://www.mosmanpark.wa.gov.au/council/council/deputation-or-ask-a-public-question/
Alternatively, you can drop your completed deputation form at the Town’s administration centre prior to the meeting.
Report of Recommendation
A report of recommendation has been written by the assessing officer for Councillors to consider in the decision-making process. This report is included in the agenda which is made available for public view on the Town’s website, on Friday 18 July 2025.
To access the agenda when it’s made publicly available please go to: https://www.mosmanpark.wa.gov.au/council/council/agendas-minutes/
The final masterplan is being considered by Council for adoption at the July Council Meetings 2025 as follows:
- Agenda Forum – Tuesday 22 July 2025
(Discuss and seek points of clarification)
- Ordinary Council meeting - Tuesday 29 July 2025
(Decision making meeting)
Both meetings are open to the public to attend which are held at the Town’s Administration Centre, 1 Memorial Drive, Mosman Park at 6pm.
Presenting to Council
If you would like to present to Councillors at either meeting, or both, please complete a Deputation form and send it directly to: eo-ceo@mosmanpark.wa.gov.au and admin@mosmanpark.wa.gov.au before the meeting. Deputation forms can be found here: https://www.mosmanpark.wa.gov.au/council/council/deputation-or-ask-a-public-question/
Alternatively, you can drop your completed deputation form at the Town’s administration centre prior to the meeting.
Report of Recommendation
A report of recommendation has been written by the assessing officer for Councillors to consider in the decision-making process. This report is included in the agenda which is made available for public view on the Town’s website, on Friday 18 July 2025.
To access the agenda when it’s made publicly available please go to: https://www.mosmanpark.wa.gov.au/council/council/agendas-minutes/
-
Update June 2025
Share Update June 2025 on Facebook Share Update June 2025 on X (formerly Twitter) Share Update June 2025 on Linkedin Email Update June 2025 linkAs part of our commitment to delivering a thorough and community-focused plan, the Town has incorporated additional processes to ensure we captured the best outcomes for the area.
The additional processes included:
- Targeted consultation with business owners from 31 March to 9 April 2025; and
- Design Review Panel on 14 April 2025 to review and provide recommendations of the proposal.
The new steps have extended our original timeline; however they are considered essential to ensuring that the final streetscape masterplan for Glyde Street reflects the needs and aspirations of all stakeholders.
The Town is currently working with our consultants to respond to Aboriginal engagement outcomes, recommendations of the Design Review Panel and public submissions. There will be some changes to the plan as a result, however, a major re-design is not expected.
An update will be provided when the modified plans are finalised and due to be sent to council for final adoption. The Town anticipates a final decision for the July 2025 Ordinary Council Meeting (OCM).
As part of our commitment to delivering a thorough and community-focused plan, the Town has incorporated additional processes to ensure we captured the best outcomes for the area.
The additional processes included:
- Targeted consultation with business owners from 31 March to 9 April 2025; and
- Design Review Panel on 14 April 2025 to review and provide recommendations of the proposal.
The new steps have extended our original timeline; however they are considered essential to ensuring that the final streetscape masterplan for Glyde Street reflects the needs and aspirations of all stakeholders.
The Town is currently working with our consultants to respond to Aboriginal engagement outcomes, recommendations of the Design Review Panel and public submissions. There will be some changes to the plan as a result, however, a major re-design is not expected.
An update will be provided when the modified plans are finalised and due to be sent to council for final adoption. The Town anticipates a final decision for the July 2025 Ordinary Council Meeting (OCM).
-
Engagement now open for Glyde Street Masterplan
Share Engagement now open for Glyde Street Masterplan on Facebook Share Engagement now open for Glyde Street Masterplan on X (formerly Twitter) Share Engagement now open for Glyde Street Masterplan on Linkedin Email Engagement now open for Glyde Street Masterplan linkThe Town of Mosman Park is developing a Streetscape Masterplan for Glyde Street to enhance its functionality, aesthetics, and community appeal as the Town's main street and gateway into our local area.
This initiative was identified through various consultation exercises with the community in 2017, 2019 and 2023. The community feedback during the development of the draft Mosman Park Village Precinct Structure Plan and previous Town Centre plan highlighting the importance of improving Glyde Street as a key local destination.
Your feedback is essential to ensure the masterplan reflects the needs and aspirations of the community. Please take a few minutes to complete this survey and help shape the future of Glyde Street.
Have your say on the Glyde Streetscape Masterplan - Survey closes 13 March 2025
The Town of Mosman Park is developing a Streetscape Masterplan for Glyde Street to enhance its functionality, aesthetics, and community appeal as the Town's main street and gateway into our local area.
This initiative was identified through various consultation exercises with the community in 2017, 2019 and 2023. The community feedback during the development of the draft Mosman Park Village Precinct Structure Plan and previous Town Centre plan highlighting the importance of improving Glyde Street as a key local destination.
Your feedback is essential to ensure the masterplan reflects the needs and aspirations of the community. Please take a few minutes to complete this survey and help shape the future of Glyde Street.
Have your say on the Glyde Streetscape Masterplan - Survey closes 13 March 2025
- What is the Glyde Street Streetscape Masterplan?
- Why does Glyde Street need a masterplan?
- Who developed the Masterplan?
- What are the key objectives of the masterplan?
- Why is the project being delivered in stages?
- What does Stage 1 include?
- Will parking be affected during Stage 1 construction?
- Will there be changes to footpaths, roads and crossings?
- How will the streetscape improvements support businesses?
- Will the completed project result in fewer parking bays on Glyde Street?
- What role do trees and landscaping play in the project?
- How is the project being funded?
- How can I stay up to date?
-
2024–2025 – Masterplan development and community engagement
Glyde Street - Streetscape Master Plan has finished this stageThe Town engaged PLACE Laboratory to develop a Streetscape Masterplan for Glyde Street. The project included community and targeted business engagement, Aboriginal engagement, a Design Review Panel review and opportunities for the community to provide feedback on the draft masterplan.
-
July 2025 – Streetscape Masterplan adopted
Glyde Street - Streetscape Master Plan has finished this stageFollowing community engagement and further design development, Council adopted the Glyde Street Streetscape Masterplan in July 2025.
-
August 2025 – Community notified of Council decision
Glyde Street - Streetscape Master Plan has finished this stageThe Town notified project stakeholders and community members who had participated in the consultation of Council’s decision to adopt the Streetscape Masterplan.
-
September 2026 – Stage 1 construction
Glyde Street - Streetscape Master Plan is currently at this stageStage 1 works will deliver improvements to the northern side of Glyde Street, including new paving and landscaping.
- Paving works: October 2026
- Tree planting: June 2027
The works are expected to continue over the coming months, with construction staged to minimise impacts on local businesses, pedestrians and road users.
-
2026–2027 | Detailed design and consultation
this is an upcoming stage for Glyde Street - Streetscape Master PlanDetailed design for future stages will continue, including civil design, Aboriginal Elder and artist consultation, and community consultation on the landscape design.
-
2027–2028 – Stage 2 roadway works
this is an upcoming stage for Glyde Street - Streetscape Master PlanStage 2 will focus on roadway reconstruction, including kerbing, pedestrian crossings and traffic calming.
Construction is currently anticipated during the 2027/28 financial year, subject to completion of the detailed design and project planning.
-
2028–2029 – Stage 3 public realm works
this is an upcoming stage for Glyde Street - Streetscape Master PlanStage 3 will deliver public realm improvements to the southern side of Glyde Street.
These works are anticipated to follow the completion of developments along this side of the street, with portions adjacent to developments expected to be delivered by the relevant developer.
Construction is currently anticipated during the 2028/29 financial year.
-
Project Officer – Parks and Environment
DH -
Director of Operations
PQ